Project Overview
Concentrator Wet Circuit Civils
This project includes:
- 2 silos
- 2 ball mills
- Primary and secondary flotation systems
- Associated thickeners
- Infrastructure buildings
Approximate Major Quantities:
- 1,000 tons of rebar
- 28,000 m² of mesh reinforcement
- 10,000 m³ of concrete
- 12,000 m² of form work
- 30,000 m³ of restricted earthworks